Concrete structures often appear to be continuous, solid masses. In practice, many are built through a sequence of separate concrete pours, sometimes taking place days or even weeks apart.
Whether constructing a reinforced concrete retaining wall, a basement, a bridge deck or a water storage tank, engineers must consider how these separate pours will behave once the structure is complete.
This is where construction joints become important.
Although they may appear to be a relatively minor construction detail, their location, design and execution can significantly affect structural performance, durability and watertightness.
Understanding construction joints is therefore essential for both design engineers and those responsible for supervising concrete works on site.
What Is a Construction Joint?
A construction joint is the interface between concrete placed at different times. It is formed when fresh concrete is placed against an earlier pour that has already hardened.
These interfaces are also commonly called daywork joints.
For example, when constructing a reinforced concrete water tank, the base slab may be poured first, followed several days later by the walls. The horizontal interface between the slab and the walls forms a construction joint.
Construction joints can be horizontal or vertical, depending on the element and construction sequence.
As explained by the Concrete Society, these joints must be constructed carefully to transfer the required forces and prevent leakage where watertightness is necessary.
Why Are Construction Joints Necessary?
It is rarely practical to construct a large concrete structure in one continuous operation.
Concrete placement is constrained by several factors, including delivery rates, available labour, formwork capacity, access arrangements and the time available for placing and compacting concrete.
Construction joints allow engineers and contractors to divide a structure into manageable sections while maintaining its intended performance.
Consider a substantial reinforced concrete retaining wall. Constructing the entire wall in a single pour could impose considerable pressure on the formwork and create difficulties with concrete delivery and compaction.
Dividing the wall into planned pours can make construction safer and more manageable.
However, the position of each joint must be considered during design. The structural forces acting across the interface, reinforcement arrangement and construction sequence all influence where joints should be located.
Structural Continuity: How Do Separate Pours Work Together?
One of the most important functions of a construction joint is transferring forces between separate concrete pours.
A properly designed reinforced concrete structure may need to transmit compression, tension and shear across a construction joint.
For example, consider a retaining wall subjected to lateral earth pressure. The connection between the wall and its base must transfer the forces required by the structural design.
Several mechanisms can contribute to load transfer:
Concrete interface resistance: Bonding, cohesion and friction contribute to resistance along the contact surface.
Aggregate interlock: A suitably roughened interface helps the two concrete surfaces resist relative sliding.
Reinforcement continuity: Appropriately anchored reinforcement crossing the joint transfers forces and helps maintain structural continuity.
Eurocode 2, BS EN 1992-1-1, provides methods for assessing shear transfer across interfaces between concrete cast at different times.
The design considers factors including interface roughness, reinforcement and stresses acting across the joint.
Importantly, simply providing reinforcement through a construction joint does not automatically guarantee adequate structural performance. The complete connection must satisfy the relevant design requirements.
Watertightness: Why Construction Joints Can Become Leakage Paths
Construction joints are particularly important in structures exposed to water.
Examples include underground basements, reservoirs, sewage treatment tanks, pumping stations and flood defence structures.
Even when the surrounding concrete has low permeability, the interface between separate pours can provide a preferential pathway for water.
This becomes particularly significant where groundwater pressure acts against a basement wall or where a tank must retain water.
Engineers commonly specify waterstops to control water movement through construction joints.
Depending on the design, these may include embedded PVC waterbars, hydrophilic strips that swell when exposed to water, coated metal waterstops or injectable hose systems.
The selected system must be compatible with the joint geometry, anticipated water pressure and construction sequence. Continuity through corners and junctions is also essential.
For liquid-retaining structures, BS EN 1992-3 provides additional design requirements. For below-ground waterproofing, BS 8102:2022 provides guidance on protection against water ingress.
Construction Joints Are Different from Movement Joints
Construction joints are sometimes confused with contraction and expansion joints, although their intended functions differ.
A construction joint connects concrete placed at different times and normally seeks to maintain the required structural continuity.
A contraction joint, sometimes called a control joint, encourages cracking to occur along a predetermined line as concrete shrinks.
An expansion or isolation joint provides separation between adjoining concrete elements to accommodate movement.
These distinctions influence reinforcement detailing, joint fillers, sealants and waterstop arrangements.
A construction joint can also be designed to accommodate movement, but this must be an intentional part of the structural design.
Another relevant term is a cold joint. According to the Concrete Society, cold joints can develop when delays between placing successive batches allow the earlier concrete to begin setting before the later concrete is properly integrated.
Unlike a planned construction joint, this situation may create an unintended plane of weakness.
Real-World Examples: Lessons from Water Infrastructure
Weirwood Water Treatment Works, England
A refurbishment project at Weirwood Water Treatment Works demonstrates the practical consequences of water ingress through concrete joints.
During the refurbishment of a concrete storage tank, groundwater was found entering through cracks in the soffit and construction joints within the slab and walls.
According to the specialist contractor, Corroless Eastern, the water ingress was more extensive than initially anticipated.
The refurbishment involved water-stopping resin treatments, joint sealing and specialist waterproofing bandages.
The case demonstrates how existing construction joints can become significant water ingress pathways, requiring extensive remedial works during a structure's operational life.
Source: Corroless Eastern, Weirwood Water Treatment Works.
Crossrail Farringdon Station, London
The construction of the Crossrail access shaft at Farringdon provides another example of the importance of joint detailing.
The approximately 200 m² base slab was situated around 20 metres below ground level.
According to Sika's project case study, the dense reinforcement and complex junction between the base slab and sprayed concrete lining made conventional waterbar arrangements difficult.
A combination of waterproofing membranes and specialist joint-sealing systems was selected to address the risk of water ingress at these interfaces.
The example illustrates why construction joints should be considered during the design process, particularly where complex geometry or congested reinforcement restricts conventional detailing.
Source: Sika, Crossrail Farringdon Case Study.
What Should Engineers Check on Site?
The quality of a construction joint depends heavily on its execution.
Before placing concrete against an existing pour, engineers should verify several important conditions.
Joint location: Confirm that the joint is positioned in accordance with the approved design and construction methodology. Any proposed relocation should be reviewed by the responsible designer.
Surface preparation: Remove laitance, loose material, contamination and debris. The Concrete Society recommends appropriate brushing or mechanical preparation to produce a suitable bonding surface.
Reinforcement: Check that reinforcement crossing the joint has the required position, cover, continuity and anchorage.
Waterstops: Where specified, verify that waterstops are correctly positioned, securely fixed and continuous through junctions.
Concrete placement: Ensure that fresh concrete can be placed and compacted effectively against the existing surface, particularly around congested reinforcement and waterstops.
Engineers should also confirm compliance with project specifications and the relevant requirements of BS EN 13670, Execution of concrete structures.
These checks should take place before the joint becomes concealed by the subsequent pour.
Conclusion
Construction joints are an unavoidable feature of many concrete structures, but their performance should never be taken for granted.
They allow complex structures to be constructed in manageable stages while ensuring that separate concrete pours can function together as intended.
Their effectiveness depends on three fundamental considerations: appropriate design, correct detailing and competent site execution.
For engineers involved in concrete design or construction, understanding these interfaces is an important part of delivering safe, durable and reliable infrastructure.
Continue Developing Your Engineering Knowledge
Explore more technical articles from Civil Engineered for Success and share your questions in the comments. Subscribe to the CEFS Weekly Briefing for regular engineering insights, or explore our bespoke training packages to develop your professional and technical competence.
References and Further Reading
The Concrete Society, Construction Joints: Horizontal
The Concrete Society, Construction Joints: Vertical
BSI, BS EN 1992-3:2006, Liquid Retaining and Containing Structures
BSI, BS EN 13670:2009, Execution of Concrete Structures
BSI, BS 8102:2022, Protection of Below Ground Structures Against Water Ingress